Somerset Rivers Authority (SRA) Board decisions 17 March 2023

A summary of what happened at the Somerset Rivers Authority (SRA) Board meeting on 17 March 2023. Only items about which decisions were taken on the day are featured below.

Item 3: Minutes of the meeting on 3 March 2023

It was agreed that the minutes of the SRA Board Meeting held on 3 March 2023 should be signed as accurate.

Item 5: River Sowy-King’s Sedgemoor Drain Enhancements Scheme (Phase 1)

As recommended, the SRA Board agreed to pause further work on Phase 1 whilst options to deliver the project at lower risk and lower cost are explored.

As recommended, the Board also agreed that all SRA partner organisations continue to work together to take the steps necessary to complete Phase 1 works.

Item 6: SRA Enhanced Programme Development 2024-25

As recommended, the SRA Board approved extending invitations for proposals for SRA funding for the 2024-25 Enhanced Programme beyond just the SRA partners.