Following a successful trial of water injection dredging techniques along a short stretch of the River Parrett on the northern edge of the village of Moorland (see below), plans are being made to increase the capacity of the River Parrett between Northmoor and the M5.

The target date for action is early 2021.
Progress has been hampered by coronavirus pandemic restrictions, but the SRA’s determination is to continue to reduce local flood risks.
The works proposed would complement numerous activities carried out since the floods of 2013-14, including pioneer dredging in 2014 and 2016, maintenance dredging in 2015, 2016, 2017, 2018 and January 2020, and regular silt monitoring.
The project is being managed for the SRA by the Parrett IDB, working closely with the Environment Agency.
Somerset Rivers Authority is using Growth Deal funding from the Heart of the South West Local Enterprise Partnership.